F7009. Warehouse buildings, Gross Floor Area (GFA)

F7009. Warehouse buildings, Gross Floor Area (GFA)

Inside wall 0,5 m
2 / m
2 GFA

Inside wall finishing: 1,0 finishing/m
2 GFA.

Cost of central heating such as CV boilers and air heaters are included in (56) heat distribution.

Main element Description Specialty Price per m2 GFA
(43) Floor finish Monolith 11,-
Armor screed Standard flatness requirement 30,-
Increased flatness requirement 38,-
Mastic asphalt 48,50
Epoxy coating 35,-
Polyurethane floor finish 52,50
Magnesiet 45,50
Anhydrite 22,-
(51)/(56) Heat generation / heat distribution Hot water heating 15 °C 32,-
Gas heating 5 °C 25,-
15 °C 15,-
(61) Central electrical facilities Safety grounding NEN 1010 1,-
Cable ducts and cable trays 3,-
Low voltage main distributor 1,-
(62) Power supply Combined light distribution device and power supply 2,-
Powerplant general 2,-
(63) Lighting Lighting installation 150 Lux, conventional 15,-
250 Lux, conventional 23,-
Emergency lighting installation 2,-
(64) Communication Sound installation 4,-
(65) Security Fire alarm evacution installation 7,-
Burglar alarm installation Simple 2,-
Hose reel and fire extinguishers 3,-