F7001. Production buildings, constructed area

F7001. Production buildings, constructed area

The cost of main element (11) earthworks, cut sods is included in the main element (13) floors on foundation.

The cost of main element (11) earthworks, excavating foundation trench is included in the main element (16) foundation construction

Main element Activity Description Price per m2 constructed area
(11) Earthworks Sod removal and ground filling 10,-
Soil improvement depth 1 m 25,-
depth 2 m 49,50
Terrain fill height 1 m 27,-
(13) Non suspended floors at ground level (beds) Concrete on steel 20 kN/m2 44,50
30 kN/m2 62,50
50 kN/m2 74,-
Concrete on piles 20 kN/m2 87,-
30 kN/m2 100,-
50 kN/m2 151,-
Asphalt 30,-
Stelcon precast concrete plate 140 mm 52,50
Floor insulation 16,-
(17) Pile foundation Concrete pile, prefab Floorload 20 kN/m2, length 10 m 19,-
Floorload 20 kN/m2, lenght 18 m 36,50
Floorload 20 kN/m2, length 25 m 47,50
Floorload 30 kN/m2, length 10 m 29,-
Floorload 30 kN/m2, length 18 m 50,50
Floorload 30 kN/m2, length 25 m 67,-
Floorload 50 kN/m2, length 10 m 41,50
Floorload 50 kN/m2, length 18 m 70,-
Floorload 50 kN/m2, length 25 m 94,-