F4016. Main supporting constructions

F4016. Main supporting constructions
Part Type Model Unit Price per unit
From Till
Steel frame Production building Single layer m2 GFA 110,- 225,-
Multi layer m2 GFA 255,- 455,-
Warehouse building Clear height 7 m m2 GFA 110,- 185,-
Office building Hollow core slabs m2 GFA 100,- 125,-
Prefab concrete floorplates m2 GFA 110,- 150,-
Steel frame Coated kg 2,50 4,-
Galvanized kg 3,- 5,-
Fire resistant spraying Beams and columns 60 min. fire resistant m2 81,- 127,-
90 min. fire resistant m2 122,- 188,-
Fire resistant coating Beams and columns 60 min. fire resistant m2 51,- 66,-
90 min. fire resistant m2 81,- 112,-
Concrete frame Poured during construction m2 GFA 270,- 390,-
Prefab m2 GFA 275,- 400,-
Concrete wall Stabilisation wall m3 865,- 1.075,-
Concrete column Square m3 850,- 1.250,-
Concrete beam Cantilever beam m3 700,- 1.200,-