F4002. Excavations and backfilling
F4002. Excavations and backfilling
| Activity | Method | Specification | Price per m3 | |
|---|---|---|---|---|
| From | Till | |||
| Excavation, loading and removal from site | Mechanically | Excavation >1.000 m3 including sampling and landfill cat. 0 | 11,- | 22,- |
| Excavation and loading | Mechanically | Excavation >1.000 m3 | 6,10 | 11,70 |
| Excavate | Manually | 45,- | 61,50 | |
| Dispose of surplus soil | Distance depot 3 km | To depot or on site | 5,80 | 9,80 |
| Backfilling | Manually | 22,50 | 31,- | |
| Backfilling and compacting | Mechanically | Exclusive delivery soil/sand | 6,- | 12,50 |
| Soil supply | From depot on site | 6,- | 12,50 | |
| Sand delivery | 16,- | 32,- | ||