B4001. Complete assembled underground piping system

B4001. Complete assembled underground piping system

Prices are based on a length of at least 10 km in a relatively open outside infrastructure.

Variation

Prices are strongly influenced by:

  • depth;
  • geography;
  • soil type;
  • number of road and water crossings;
  • insulation;
  • working pressure;
  • agriculture and land situation;
  • material prices.

Included:

  • indirect costs (construction management), general overhead cost;
  • design (pressure 60 Bar, temperature 50 °C, no thermal insulation);
  • compensation of land owners and land users;
  • materials and erection;
  • testing and commissioning;
  • temporary building facilities;
  • small road- and water crossings (2 drills of 400 meter each);
  • ground cover 1,25 meter.

Excluded:

  • large river-, channel- and road crossings;
  • PIG launcher, receiving station and block valves;
  • licences and tax;
  • owners internal costs.
Diameter in inches Price per m CS Price per m duplex
From Till From Till
4 234,- 440,- 135,- 600,-
6 278,- 520,- 462,- 855,-
8 320,- 610,- 600,- 1.120,-
10 375,- 685,- 725,- 1.380,-
12 420,- 780,- 890,- 1.670,-
16 430,- 810,-
20 460,- 840,-
24 550,- 1.020,-
30 710,- 1.330,-
36 940,- 1.750,-