F4009. Pile foundations
F4009. Pile foundations
Minimum number of 50 piles.
Inclusive:
- (revised) calculations, - drawings, piling plan;
- measuring and setting out;
- reinforcement and earthing bars;
- removal of drilling mud and contaminated ground;
- acoustic measuring;
- piles cutting and removal of pile cut offs.
Exclusive:
- excavation and test trenches;
- dock plates, fencing etc.
| Type | Specification | Price per m | |
|---|---|---|---|
| From | Till | ||
| Prefabricated concrete piles | Maximal 290 x 290 mm | 31,- | 40,- |
| 320 x 320 mm till 380 x 380 mm | 43,- | 57,- | |
| Minimal 400 x 400 mm | 64,- | 80,- | |
| Mortar piles | Light construction | 74,- | 90,- |
| Heavy construction | 95,- | 116,- | |
| Atlas-/Fundex-/Vibro piles | Light construction | 85,- | 106,- |
| Heavy construction | 111,- | 137,- | |
| Tubexpiles | 316,- | 405,- | |